New Housing Construction
Length of Construction (in months)

By:

  1. Dwelling Types
  2. Intended Markets

Display Options:

  1. Survey Zones
  2. Census Subdivisions
  3. Neighbourhoods
  4. Census Tracts
  5. Historical Time Periods

Note:

Changes to display settings will reset date settings to most recent data. Available display settings are subject to change based upon data available.

Toronto — Average Length of Construction (in months) by Dwelling Type by Zone

  Single Semi-Detached Row Apartment All
Toronto 14.5 12.4 23.9 28.0 24.4
Toronto (Central) 16.5 17.0 ** 14.4 14.4
Toronto (East) 17.6 ** ** ** 17.6
Toronto (North) 0.0 ** ** ** 0.0
Toronto (West) 14.0 ** ** 18.0 17.8
Etobicoke (South) 12.8 ** ** ** 12.8
Etobicoke (Central) 15.2 ** ** 29.0 28.6
Etobicoke (North) ** ** ** ** **
York 15.8 6.0 ** 27.0 25.8
East York 15.1 ** ** ** 15.1
Scarborough (Central) 13.0 ** ** ** 13.0
Scarborough (North) 23.2 ** ** ** 23.2
Scarborough (East) 13.5 ** ** ** 13.5
North York (Southeast) ** ** 73.0 ** 73.0
North York (Northeast) 19.2 ** ** 59.6 59.0
North York (Southwest) 19.4 ** ** ** 19.4
North York (N.Central) 19.8 ** ** ** 19.8
North York (Northwest) ** ** 16.1 ** 16.1
Mississauga (South) 17.3 ** 21.0 ** 19.2
Mississauga (Northwest) ** ** ** ** **
Mississauga (Northeast) 22.0 ** ** ** 22.0
Brampton (West) 11.0 ** 11.0 ** 11.0
Brampton (East) 9.1 ** 11.7 12.5 12.0
Oakville ** ** ** ** **
Caledon 12.0 12.0 10.7 ** 11.4
Richmond Hill/Vaughan/King 18.6 ** 20.3 ** 18.8
Aurora, Newmkt, Whit-St. 14.8 15.5 5.0 ** 14.5
Markham 14.1 ** 12.3 ** 12.8
Pickering/Ajax/Uxbridge 11.0 ** 12.1 ** 11.9
Milton/Halton Hills 10.0 ** 11.5 ** 10.6
Orangeville/Mono ** ** ** ** **
Bradford/West Gwillimbury/New Tecumseth 11.2 12.8 ** ** 11.8
Notes:
  • CMA, CA and CSD definitions are based on 2016 Census Geography Definitions