New Housing Construction
Length of Construction (in months)

By:

  1. Dwelling Types
  2. Intended Markets

Display Options:

  1. Survey Zones
  2. Census Subdivisions
  3. Neighbourhoods
  4. Census Tracts
  5. Historical Time Periods

Note:

Changes to display settings will reset date settings to most recent data. Available display settings are subject to change based upon data available.

Calgary — Average Length of Construction (in months) by Intended Market by Zone

  Homeowner Rental Condo Co-Op All
Calgary 7.9 8.4 9.3 ** 8.2
Downtown ** ** ** ** **
Beltline ** ** ** ** **
North Hill 12.0 ** ** ** 12.0
Southwest 9.2 13.5 12.2 ** 11.7
Southeast 8.0 9.7 11.3 ** 9.2
Northwest 7.1 8.6 8.3 ** 7.5
Northeast 8.2 11.5 10.6 ** 9.4
Chinook 16.0 ** ** ** 16.0
Fish Creek 6.9 7.1 7.6 ** 7.2
Other Centres 8.5 1.9 ** ** 6.5
Notes:
  • CMA, CA and CSD definitions are based on 2021 Census Geography Definitions