New Housing Construction
Length of Construction (in months)

By:

  1. Dwelling Types
  2. Intended Markets

Display Options:

  1. Survey Zones
  2. Census Subdivisions
  3. Neighbourhoods
  4. Census Tracts
  5. Historical Time Periods

Note:

Changes to display settings will reset date settings to most recent data. Available display settings are subject to change based upon data available.

Calgary — Average Length of Construction (in months) by Intended Market by Zone

  Homeowner Rental Condo Co-Op All
Calgary 7.0 13.3 20.2 ** 12.5
Downtown ** 9.0 ** ** 9.0
Beltline ** ** ** ** **
North Hill 13.2 13.0 ** ** 13.0
Southwest 11.5 14.0 8.9 ** 13.5
Southeast 6.5 10.1 22.2 ** 13.4
Northwest 7.4 14.1 16.0 ** 12.0
Northeast 6.6 7.0 37.3 ** 20.3
Chinook ** 18.0 ** ** 18.0
Fish Creek 6.9 15.5 10.4 ** 11.7
Other Centres 6.6 12.4 7.0 ** 7.0
Notes:
  • CMA, CA and CSD definitions are based on 2021 Census Geography Definitions