New Housing Construction
Length of Construction (in months)

By:

  1. Dwelling Types
  2. Intended Markets

Display Options:

  1. Survey Zones
  2. Census Subdivisions
  3. Neighbourhoods
  4. Census Tracts
  5. Historical Time Periods

Note:

Changes to display settings will reset date settings to most recent data. Available display settings are subject to change based upon data available.

Vancouver — Average Length of Construction (in months) by Intended Market by Zone

  Homeowner Rental Condo Co-Op All
Vancouver 15.6 22.7 25.7 ** 23.0
West End/Stanley Park ** ** ** ** **
English Bay ** ** ** ** **
Downtown ** ** ** ** **
South Granville/Oak ** 22.0 ** ** 22.0
Kitsilano/Point Grey 19.0 18.0 ** ** 18.8
Westside/Kerrisdale 17.8 19.3 38.7 ** 33.1
Marpole 15.1 18.0 ** ** 16.3
Mount Pleasant/Renfrew Heights 16.9 22.9 17.6 ** 22.3
East Hastings 13.8 15.4 20.0 ** 14.7
Southeast Vancouver 12.6 17.3 14.8 ** 16.5
University Endowment Lands ** ** ** ** **
Central Park/Metrotown 15.7 16.7 ** ** 16.0
Southeast Burnaby 16.1 16.1 ** ** 16.1
North Burnaby 14.3 17.6 14.0 ** 15.1
New Westminster 20.5 19.0 ** ** 19.8
North Vancouver CY 25.0 33.0 13.8 ** 16.3
North Vancouver DM 14.3 15.5 ** ** 14.8
West Vancouver 38.0 ** ** ** 38.0
Richmond 16.0 15.3 ** ** 15.7
Delta 12.0 11.2 ** ** 11.5
Surrey 14.2 25.2 16.6 ** 22.5
White Rock 13.5 15.0 ** ** 14.9
Langley City and Langley DM 12.2 10.6 ** ** 11.4
Tri-Cities 24.6 35.8 27.7 ** 28.7
Maple Ridge/Pitt Meadows 10.4 16.0 ** ** 11.7
Notes:
  • CMA, CA and CSD definitions are based on 2021 Census Geography Definitions