New Housing Construction
Length of Construction (in months)

By:

  1. Dwelling Types
  2. Intended Markets

Display Options:

  1. Survey Zones
  2. Census Subdivisions
  3. Neighbourhoods
  4. Census Tracts
  5. Historical Time Periods

Note:

Changes to display settings will reset date settings to most recent data. Available display settings are subject to change based upon data available.

Vancouver — Average Length of Construction (in months) by Intended Market by Zone

  Homeowner Rental Condo Co-Op All
Vancouver 15.9 16.8 30.2 ** 26.9
West End/Stanley Park ** ** ** ** **
English Bay ** ** ** ** **
Downtown ** ** ** ** **
South Granville/Oak ** ** 30.0 ** 30.0
Kitsilano/Point Grey 29.5 20.7 22.0 ** 23.4
Westside/Kerrisdale 23.8 13.0 ** ** 17.9
Marpole 23.8 15.0 ** ** 19.0
Mount Pleasant/Renfrew Heights 14.0 12.3 ** ** 13.1
East Hastings 13.6 11.8 37.0 ** 26.1
Southeast Vancouver 12.5 11.8 ** ** 12.1
University Endowment Lands ** ** ** ** **
Central Park/Metrotown 15.3 15.3 ** ** 15.3
Southeast Burnaby 26.3 17.3 25.1 ** 25.0
North Burnaby 19.5 19.5 31.8 ** 31.6
New Westminster 14.8 13.0 32.0 ** 31.7
North Vancouver CY 18.9 20.2 ** ** 19.4
North Vancouver DM 17.0 15.3 ** ** 16.3
West Vancouver 37.8 ** ** ** 37.8
Richmond 15.5 28.1 35.0 ** 32.9
Delta 15.0 15.6 ** ** 15.2
Surrey 15.9 15.0 10.0 ** 13.9
White Rock 21.0 21.0 ** ** 21.0
Langley City and Langley DM 10.2 16.6 7.5 ** 14.0
Tri-Cities 14.6 13.1 11.9 ** 13.3
Maple Ridge/Pitt Meadows 15.3 15.3 ** ** 15.3
Notes:
  • CMA, CA and CSD definitions are based on 2021 Census Geography Definitions